10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
The CBL-Prometric exam has 50 questions and runs 2 hours.
These 10 free CBL-Prometric questions are organized by exam domain, so you can see how each part of the Contractor Business and Law Examination (Prometric) blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Business Organization and Management 6% of exam
Question 1
For two years, a contractor allowed its project superintendent to rent equipment costing up to $10,000, and the company paid those invoices without objection. The company later reduced the superintendent's internal limit to $5,000 but never notified its regular rental supplier. The superintendent then rents $8,000 of equipment. What type of authority most likely binds the contractor to the supplier?
Show answer & explanation
Correct answer: D - Apparent authority created by the contractor's prior conduct
Domain 2: Licensing 8% of exam
Question 2
State B requires an issued contractor license before a construction contract may be executed. A contractor licensed in State A qualifies for State B reciprocity, which waives the equivalent examination, but has not filed the State B application or received a State B license. What must happen before the contractor signs the project contract?
Show answer & explanation
Correct answer: D - Complete State B's licensing process and receive authorization to contract
Domain 3: Estimating and Bidding 8% of exam
Question 3
An estimator has $240,000 in direct cost, $30,000 in project overhead, $15,000 in home-office overhead, and $15,000 in contingency. A separate $20,000 owner allowance will be reimbursed at actual cost and is excluded from the contractor's margin base. Which bid price, before tax and the reimbursable allowance, produces a 20% gross margin?
Show answer & explanation
Correct answer: C - $375,000
Domain 4: Contracts 12% of exam
Question 4
An excavation uncovers a concealed utility that the contract treats as an excusable differing site condition. The contractor promptly documents a 14-day critical-path impact and requests an extension. Without issuing a formal acceleration directive, the owner leaves the request unresolved, insists on the original completion date, and the contractor adds a night shift and premium freight. The added-cost claim is best characterized as:
Show answer & explanation
Correct answer: B - Constructive acceleration
Domain 5: Project Management 12% of exam
Question 5
All activities use finish-to-start logic with zero lag. Activity A takes 3 days. After A, B takes 6 days and C takes 4 days. D takes 3 days after B; E takes 2 days after C. Final activity F takes 1 day and requires both D and E. If C finishes 2 days later than planned and all other durations remain unchanged, which schedule conclusion follows?
Show answer & explanation
Correct answer: B - Project completion is unchanged, and the C-E branch retains 1 day of total float
Domain 6: Risk Management 6% of exam
Question 6
A subcontract requires the general contractor to be an additional insured for ongoing and completed operations on a primary and noncontributory basis. The subcontractor provides only a certificate naming the general contractor as certificate holder. Which action best closes the coverage gap?
Show answer & explanation
Correct answer: C - Obtain and review the policy endorsements that grant the required additional-insured coverage
Domain 7: Safety - OSHA 6% of exam
Question 7
During the morning inspection, a competent person finds employees entering a 7-foot-deep trench in previously disturbed soil. The walls are vertical, no protective system is installed, and excavated material is piled 18 inches from the edge. A secured ladder is already within 25 feet, and no stable-rock determination has been made. What must occur before employees reenter?
Show answer & explanation
Correct answer: A - Keep employees out, install a compliant protective system, and move the spoil at least 2 feet back
Domain 8: Labor Laws 16% of exam
Question 8
A nonexempt carpenter works 45 hours in one workweek at $24 per hour and earns a $90 production bonus promised in advance for meeting the week's output target. Straight time is paid for all 45 hours. Under the FLSA regular-rate method, what total gross pay is due for the week?
Show answer & explanation
Correct answer: D - $1,235
Domain 9: Financial Management 10% of exam
Question 9
Using cost-to-cost percentage of completion, a contractor has a $1,500,000 contract, $540,000 of cost incurred, $360,000 of estimated cost to complete, and $850,000 billed to date. How should the WIP position be reported?
Show answer & explanation
Correct answer: A - $50,000 underbilling, reported as a contract asset
Domain 10: Tax Laws 10% of exam
Question 10
A monthly schedule depositor accumulates $100,000 in federal employment-tax liability on a Tuesday, and no federal holiday intervenes. Which deposit obligation applies?
Show answer & explanation
Correct answer: A - Deposit by Wednesday and use the semiweekly schedule for the rest of this year and the following year
The rest of the CBL-Prometric blueprint
The CBL-Prometric exam also covers these domains. Drill them in the full free practice test:
Domain 11: Lien Laws6% of exam
That's 10 of 1,030
The full bank has 1,020 more CBL-Prometric questions with explanations.